Many internal renovations in the ACT are exempt from development application (DA) approval - but extensions, significant structural changes, new builds, demolition, and work in heritage areas typically require a DA. If your project is a knockdown rebuild, a Mr Fluffy block rebuild, or a dual occupancy development, a DA is required - those pathways have their own specific planning considerations covered on each service page. The dividing line is not always obvious, and the consequences of getting it wrong are serious: building without required approval can mean stop-work orders, fines, and mandatory demolition at your own cost. This guide explains what requires DA in the ACT, what is exempt, and how to work through the approval process efficiently. As of 1 May 2026, the ACT is transitioning from NCC 2022 to NCC 2025 - which adds new energy and accessibility requirements to most building approvals.

Important: Planning rules in the ACT are governed by the ACT Planning Act 2023 and the Territory Plan, which are updated periodically. This guide reflects the position as at April 2026. Always verify current requirements at planning.act.gov.au or with a licensed ACT builder before commencing work.

What is a Development Application (DA)?

A development application is a formal planning approval granted by the Territory Planning Authority (formerly ACTPLA). It assesses whether a proposed development - a renovation, extension, new build, or demolition - is consistent with the ACT Territory Plan, zoning rules, and applicable planning policies. A DA approval is a planning permission. It is separate from a building approval, which is issued by a registered building certifier and confirms the work complies with the Building Code of Australia.

You need both a DA (where applicable) and a building approval (for most construction work) before you can legally build.

What is Exempt from DA in the ACT?

Exempt development provisions allow certain works to proceed without a DA. In the ACT, exempt development is defined in the Territory Plan and covers works that are considered low-impact and unlikely to affect the environment, amenity, or neighbours. Key categories include:

Project Type Generally Exempt? Conditions / Notes
Internal alterations (no structural changes) Yes - generally exempt Must not affect structural elements or external appearance
Kitchen renovation (like-for-like) Yes - generally exempt Licensed plumber and electrician required; no structural changes
Bathroom renovation (like-for-like) Yes - generally exempt Building certifier required if moving fixtures; waterproofing must comply with AS 3740
Painting, flooring, internal finishes Yes - exempt No approval required
Garden shed / ancillary structure Conditional Size and height thresholds apply; must comply with setbacks
Pergola / shade structure Conditional Height, area limits, and setback rules apply
Fencing (residential) Generally exempt Height limits apply; heritage areas may require approval
Like-for-like roof replacement Generally exempt Must use same or similar material; no change to roof form
Single house extension, including a second storey Conditional Exempt only if it fully complies with the Single Dwelling Housing Development Control (storeys, height, building and solar envelopes, setbacks) and neighbours are given information; minor departures can use an exemption declaration
Heritage Properties: Exempt development provisions do not apply to registered heritage places or properties within heritage precincts. Any work - including internal alterations - on a heritage property may require approval. Check the ACT Heritage Register before assuming your project is exempt.

Updated 15 October 2026: the exemptions for houses sit in the Planning (Exempt Development) Regulation 2023 and the Single Dwelling Housing Development Control made under it. A compliant extension to a single house, including a second storey, can go ahead without a DA. If the design breaks a setback, envelope or private open space control by a minor amount, the exemption declaration route may apply. Our second storey extensions guide sets out the specific controls.

Site constraints can sit alongside planning approval. If your project involves work near a protected tree, read my tree protection guide for Canberra before finalising the design.

Exempt from a DA: the Single Dwelling Housing Development Control

Before walking through DA in detail, it's worth flagging the pathway that most homeowners don't know about and most builders try to use wherever possible. The Single Dwelling Housing Development Control, made under the Planning (Exempt Development) Regulation 2023, lets a lot of single-house extensions, alterations and additions go ahead without a Development Application at all, provided the project meets its rules.

The control is rules-based. If your project complies with the storey and height limits, the building and solar envelopes, setbacks and the other requirements, it is exempt from a DA and goes to building approval with a certifier. The benefits are real: no DA assessment time, a more certain outcome because the rules are fixed, and no public notification process. You do still need to take reasonable steps to give written information about the work, including site and elevation plans, to the adjoining residents. If the design breaks a control by a minor amount, an exemption declaration may still be possible.

Where it suits the brief, designing an extension to comply from the outset saves time, money and stress. If your designer or architect isn't familiar with the exempt development rules, that's worth raising early.

The exempt pathway won't work for every project. If you want to go beyond the setbacks or envelopes, build on a heritage-listed site, or do something the rules don't allow, you'll need a DA. But for a lot of standard extensions and alterations to single houses on RZ1 blocks, the exempt pathway is the right one.

Building Approval (BA) - separate from DA, and you still need one

One thing that catches a lot of homeowners off-guard: even if your project doesn't need a DA, it almost always still needs a Building Approval (BA). The BA is a separate process from planning approval and runs through a private building certifier rather than the planning authority.

The BA confirms that your plans comply with the National Construction Code, structural requirements, energy efficiency rules, fire safety provisions and all the other technical building standards. It's the legal authorisation for actual construction work.

The BA process typically takes 2-4 weeks for a straightforward project. It can run in parallel with your planning approval (if you have one) or follow on after it. Even fully exempt developments usually still require a BA if there's actual construction work involved.

As your builder, we manage the BA process and certifier relationship on your behalf. You don't need to chase certifiers, organise inspections or deal with the technical paperwork. But you do need to know it's a real cost line ($1,500 to $4,500 typically) and a real time line (2-4 weeks added to your overall pre-construction period).

What Requires DA in the ACT?

Project Type DA Required? Notes
Ground floor home extension May be exempt, otherwise DA Exempt if it fully complies with the Single Dwelling Housing Development Control (height, envelopes, setbacks and the other controls) and adjoining residents are given written information. Otherwise a DA is required.
Second storey addition Sometimes Exempt if it fully complies with the controls, including the two storey limit and solar envelope. Many projects need a DA because of overshadowing.
Structural wall removal (open-plan) Building approval required (not DA) Structural engineer and building certifier required; not a DA matter if no external change
New residential dwelling (new build) Yes Required for all new principal dwellings
Secondary dwelling / granny flat Yes ACT has specific rules for secondary dwellings in RZ1 zones
Demolition Yes (demolition approval) Separate process; asbestos survey and management plan required
Any work on a heritage-listed property Yes Heritage Impact Statement required; Heritage Council review
Change of use Yes E.g. converting garage to habitable room; changing residential to mixed-use
Swimming pool Yes (building approval) Pool fence and barrier requirements under ACT legislation apply

The DA Application Process: Step-by-Step

1Determine whether DA is required. Review your proposed project against the exempt development provisions in the Territory Plan. Check your block's zoning at planning.act.gov.au. If your project involves an extension, structural change, demolition, or heritage property, a DA is almost certainly required. A licensed ACT builder can assess this for you at no charge as part of an initial consultation.

2Request pre-application advice (strongly recommended). The Territory Planning Authority offers a pre-application advice service. For a modest fee ($200–$600), a planning officer reviews your concept and provides written guidance on requirements and potential issues. This service is particularly valuable for heritage areas, unusual block configurations, and complex applications. It reduces the risk of costly amendments after lodgement.

3Commission required documentation. You will need: a site plan showing existing and proposed structures; architectural drawings (floor plans, elevations, sections); shadow diagrams; a Statement of Environmental Effects (SEE); and for heritage properties, a Heritage Impact Statement. For structural extensions, a structural engineer's preliminary assessment and drawings are also required.

4Lodge the DA via the ACT Planning Portal (eDAPL). Applications are lodged electronically. Upload all documentation, pay the lodgement fee, and provide owner's consent. The application receives a DA reference number and is assigned to an assessing officer. For notifiable developments, a 10-business-day notification period allows neighbours to make representations.

5Assessment and decision. The assessing officer reviews the DA against the Territory Plan and relevant planning policies, considers any neighbour representations, and may refer to other agencies (Heritage, Environment, Utilities). The authority must decide within 30 business days for most residential applications under the Planning Act 2023, though complex applications take longer. The decision is approval (with or without conditions), approval with modifications, or refusal.

6Building approval. After DA approval, a separate building approval is required before construction starts. A licensed building certifier issues the building approval and, once the builder is engaged, a commencement notice before work begins. The certifier inspects at mandatory stages during construction. At completion the certifier issues a certificate of completion, and the certificate of occupancy and use is then issued through Access Canberra.

DA Costs and Timeframes: What to Budget

Item Estimated Cost Notes
Pre-application advice (Territory Planning Authority) $200–$600 Strongly recommended for complex projects
Architectural drawings (DA set) $3,000–$15,000 Depends on project complexity; includes site plan, elevations, sections
Structural engineer (preliminary) $1,500–$4,000 Required for extensions and structural changes
Heritage Impact Statement $2,000–$8,000 Required for registered heritage places and precincts
ACT DA lodgement fee $500–$5,000+ Calculated on estimated development cost
Building certifier (certification) $2,000–$6,000 Engaged separately after DA approval; required for all construction
Energy efficiency assessment $500–$1,500 May be required for extensions; EER compliance under ACT regulations
Total DA process cost (typical residential extension) $8,000–$25,000 Excludes construction costs

DA Timeframes

Application Type Typical Assessment Time
Standard residential extension or new build 6–12 weeks
Notifiable development (neighbour notification required) 8–14 weeks
Heritage-listed property 12–24 weeks
Impact-assessable development (EIS required) 6–18 months

Heritage Considerations in Canberra

The ACT has a rich heritage estate - many of Canberra's most desirable suburbs contain properties of significant historical and architectural value. Heritage listing in the ACT operates at two levels: individual place listing on the ACT Heritage Register, and precinct-level protection through Heritage Precincts in the Territory Plan.

Heritage Areas in Canberra

Suburb / Area Heritage Status Implications
Griffith Heritage Precinct (outer areas) Design review for extensions; materials and scale restrictions
Yarralumla Heritage Precinct (parts) Strict controls on external changes; Heritage Council involvement
Red Hill / Forrest / Deakin Some individually listed properties Heritage Impact Statement required for listed properties
Kingston Kingston Heritage Precinct Industrial/residential character controls; scale and materiality constraints
Campbell (Duntroon area) Individually listed properties Heritage Act 2004 applies; strict controls on alterations
Ainslie / Turner / Braddon Some individually listed properties Verify heritage status through ACT Heritage Register before planning works

To check whether your property is on the ACT Heritage Register, visit the ACT Environment, Planning and Sustainable Development Directorate heritage portal or search the ACT Heritage Register online.

Energy Efficiency Requirements (EER)

The ACT has mandatory Energy Efficiency Rating (EER) requirements for most new builds and significant renovations. Under ACT regulations, new residential buildings must achieve a minimum 6-star NatHERS rating. Extensions and significant renovations may trigger EER compliance requirements depending on the scope and whether they constitute a "significant alteration." An energy efficiency assessor must be engaged to model and certify compliance. Budget $500–$1,500 for an EER assessment.

Tips to Speed Up Your DA

Incomplete documentation at lodgement is a common cause of DA delays. If your application is missing documents or doesn't address the planning requirements, the Territory Planning Authority will ask for further information, and each round adds time. Investing in thorough documentation up front, even if it costs an extra $2,000 in design or consultant fees, is generally the more economical approach.

Practical tips to maximise your chances of a smooth, timely DA assessment:

  • Use the pre-application advice service. The Territory Planning Authority offers written pre-application advice, and it is worth using. A written pre-application response from a planning officer identifies issues before lodgement, allowing you to address them in your application rather than through RFIs.
  • Engage a town planner for complex applications. For heritage areas, unusual zoning situations, or applications near approval thresholds, a town planner's involvement in preparing the Statement of Environmental Effects and planning analysis can significantly reduce assessment time.
  • Speak to your neighbours early. For notifiable developments, neighbour objections can complicate assessment. A proactive conversation with adjoining owners before you lodge - showing them the design and addressing any concerns - reduces the likelihood of formal representations that trigger additional assessment work.
  • Don't rely on outdated information. The ACT planning system has undergone significant reform through the Planning Act 2023. Rules that applied two or three years ago may have changed. Always check current requirements at planning.act.gov.au or with a licensed builder who works actively in the ACT market.
  • Allow for the full timeline in your project schedule. It is almost impossible to compress a DA assessment below six weeks. Any renovation or extension involving a DA should have its construction programme commence after DA approval is received - not before lodgement. Building before approval is not a risk worth taking.

For context on how planning requirements affect renovation and extension project costs, see our related guides to home renovation costs in Canberra and home extension costs in Canberra.

Frequently Asked Questions

Do I need DA approval to renovate my home in the ACT?

Many internal renovations in the ACT are exempt from DA approval, including like-for-like replacements and internal alterations. Extensions, significant structural changes, new builds, demolitions, and work in heritage areas typically require DA. Always verify current requirements at planning.act.gov.au or with a licensed ACT builder before commencing - rules change, and penalties for unauthorised work are significant.

How long does a DA take to be approved in the ACT?

Standard residential DA applications are assessed within approximately 6–12 weeks in the ACT. Complex or heritage applications take longer - often 12–24 weeks. The ACT Planning Act 2023 sets assessment timeframe targets of 30 business days for standard residential applications, but information requests from the applicant pause the clock and are common for incomplete lodgements.

How much does a DA application cost in the ACT?

Total DA costs including architectural plans, structural engineer reports, heritage impact statements (if required), government lodgement fees, and building certifier fees typically total $8,000–$25,000 for a standard residential extension. Government lodgement fees alone range from $500–$5,000+ depending on estimated development cost. Pre-application advice costs $200–$600 and is strongly recommended.

What is exempt development in the ACT?

Exempt development includes works that don't require DA approval because they meet specific criteria in the Territory Plan. Examples include internal alterations, like-for-like replacements, small ancillary structures within size and setback limits, and minor fencing. Exempt development still requires a licensed builder and compliance with the Building Code of Australia - it simply doesn't require planning approval from the Territory Planning Authority.

Do heritage homes in Canberra require special approval for renovations?

Yes. Properties on the ACT Heritage Register or within a Heritage Precinct require Heritage Impact Assessment for most external works and some internal works. Heritage precincts include parts of Griffith, Yarralumla, Red Hill, Forrest, Deakin, and Kingston. Allow an additional 4–8 weeks for heritage assessment over a standard DA, and engage a qualified heritage consultant to prepare the Heritage Impact Statement.

What happens if I build without DA approval in the ACT?

Building without required DA approval in the ACT is an offence under the Planning Act 2023. The ACT Planning Authority can issue a stop-work order, require demolition of unauthorised works at the owner's cost, and impose fines. Unauthorised works create difficulties when selling your property. Retrospective approval (seeking approval after construction) is possible but not guaranteed and significantly more expensive than getting approval first.

What is a building certifier and do I need one for my renovation?

A building certifier is a licensed professional who certifies that building work complies with the Building Code of Australia. In the ACT, you need a registered certifier for any construction work requiring a building approval - including structural alterations, extensions, and new builds. Your certifier issues the building approval and commencement notice before work starts. At the end, the certifier signs off the work and the certificate of occupancy and use is issued through Access Canberra. Your builder typically arranges certifier engagement.

Disclaimer: This article provides general information only and does not constitute planning or legal advice. ACT planning rules are governed by the ACT Planning Act 2023 and the Territory Plan, which are subject to change. Always verify current requirements at planning.act.gov.au or by consulting a licensed ACT builder or registered town planner before commencing any building work.