The Canberra Renovation Guide

Real costs, real timelines and real decisions, written by a licensed ACT builder for Canberra homeowners planning a significant renovation or extension.

Written by
Jeff Rentoule
Updated
October 2026
Reading time
About 20 minutes
Chapters
10

This is the guide I wish every Canberra homeowner had before they started a renovation. Real costs, real timelines, real decisions, written by a licensed ACT builder with 19 years in the building industry and 5 years running my own business.

I’m Jeff Rentoule. I run Rentoule Projects, a small residential building business based in Canberra. Over the past five years I’ve watched too many homeowners walk into renovations carrying assumptions that cost them money, time, or both. This guide is my attempt to fix that. No corporate fluff, no sales pitch in disguise. Just what I would tell a mate over coffee if they were thinking about renovating.

Use it however you want. Read it end to end, jump to the section you need, or come back when a specific question comes up.

Chapter 01

1. The real cost of renovating in Canberra

Typical Canberra ranges for seven common project types, and why building here costs more than the eastern seaboard average.

Let’s start with the question everyone wants answered first. What does a renovation cost in Canberra in 2026?

The honest answer is “it depends.” But that’s a cop-out, so here are the ranges I see across our projects, broken out by the most common project types. These are turn-key, fixed-price figures including labour, materials, project management, and trade coordination.

Typical Canberra ranges by project type
Project typeTypical Canberra rangeWhat you get
Bathroom renovation$35,000 to $130,000+Ensuites from $35,000, main bathrooms from $45,000. Full strip-out and rebuild, custom to premium fixtures
Kitchen renovation$35,000 to $160,000+Small area kitchens from $35,000, full kitchens from $50,000. Most family kitchens with a wall removed sit at $90,000 to $120,000. Complete redesign, custom cabinetry, stone benchtops, quality appliances
Whole-house cosmetic refresh$80,000 to $250,000Paint, flooring, kitchen, bathrooms, light fittings. No structural work (not a Rentoule Projects service)
Major renovation (structural)$300,000 to $1,000,000+Walls moved, layout changed, new kitchen and bathrooms, possibly second storey
Single-storey extension$150,000 to $450,00030-60 sqm addition, usually living space or master suite, premium finishes
Second storey addition$300,000 to $700,000+Full upper floor, structural reinforcement, internal stairs, often 2-3 bedrooms
Knockdown rebuild$850,000 to $2M+Demolition, new build to your specification, typically 200-350 sqm

For deeper detail on each, I’ve written separate cost guides:

Weighing up a full rebuild? See our knockdown rebuild service.

Why Canberra costs more than the eastern seaboard average

A smaller trade pool

Three reasons. First, the trade pool is smaller. Sydney and Melbourne have an order of magnitude more builders, plumbers, electricians and tilers competing for work. We don’t. When demand peaks, prices peak harder here.

Stricter ACT regulations

Second, ACT regulations are stricter than most states. Energy efficiency requirements (EER), bushfire compliance in many suburbs, asbestos protocols on older homes, and the ACT’s particular planning rules all add cost. They also add quality, but they add cost.

A brutal climate

Third, our climate is brutal. Canberra winters demand higher-spec insulation, double or triple glazing, sealed building envelopes, and reverse-cycle systems sized for sub-zero overnights. A renovation that ignores climate performance is a renovation you’ll regret in July.

Waterfall stone island in a Weetangera kitchen renovation by Rentoule Projects
A full kitchen renovation in Weetangera. Layout, joinery and stone drive most of the difference in kitchen cost.
Next · Chapter 02How to plan your renovation properly

Chapter 02

2. How to plan your renovation properly

The five-step sequence that works, from writing the brief to locking the scope before you sign.

The biggest predictor of how a renovation goes is how much thought went in before a single trade arrived on site. Most disasters I’ve seen started with rushed planning.

Here’s the sequence that works.

Step 1: Define the brief in writing

Before you talk to anyone, write down what you want. Not “a bigger kitchen” - write down “I want an open-plan kitchen, dining and living area where the kids can do homework while I cook, with a butler’s pantry hidden from view, and a north-facing dining nook with morning sun.” The more specific you are, the easier every conversation downstream becomes.

If you can’t write your brief, you’re not ready to start. That’s not a failing - it just means the next step is conversations, not contracts.

Step 2: Set a budget you can defend

Most people set a budget by guessing what they can afford and then assuming a renovation will fit. That’s backwards. Start with the cost ranges in section 1, work out what your project realistically costs, then check whether your finance and savings cover it with a 15% buffer for variations and surprises.

If the numbers don’t work, you have three options: reduce scope, find more money, or wait. Pretending the numbers work is the most expensive option, because it leads to either a half-finished project or compromises that ruin the result.

Step 3: Get the right professionals involved early

For anything beyond a simple cosmetic refresh, you need three people in the room: a designer or architect, a builder, and a structural engineer if walls are coming out. Get all three involved before drawings are finalised. I’ve watched homeowners spend $15,000 on architectural plans only to discover the design isn’t buildable within their budget.

Some builders, including us, will do early-stage feasibility before you commit to detailed design. It saves money and frustration on both sides.

Step 4: Understand the approval pathway

Not every renovation needs a Development Application (DA), but you need to know which category yours falls into before you commit. Cosmetic and minor work often qualifies as exempt development. Structural work, extensions and second storeys may need DA approval, unless they fully comply with the exempt development rules. The rules in the ACT are specific. I’ve written a full guide on DA approvals here.

Step 5: Lock the scope before you sign

Every variation after a contract is signed costs more than it would have during planning. Sometimes a lot more. Spend the time up front to nail down inclusions, finishes, fixtures and fittings to the level of model numbers and brand names. The contract should have a defined scope, a fixed price, a payment schedule, a completion date with liquidated damages, and a written variations process.

If you want to go deeper, my step-by-step planning guide walks through the full process. And if you’d like to see how we run planning and pricing on our own projects, here’s how we work.

Two Rentoule Projects team members crouched on site talking through details on a tablet
Talking through the details on site. The decisions that save money are made before the next stage starts.
Next · Chapter 03Avoiding budget blowouts

Chapter 03

3. Avoiding budget blowouts

The line items nobody mentioned: seven cost categories that most often catch Canberra homeowners out.

The single biggest reason renovations go over budget is that the original budget didn’t include things it should have. The work itself usually costs roughly what we quoted. The blowout comes from the line items nobody mentioned.

Here are the costs I see catch homeowners out most often.

Site costs that aren’t site costs

Skip bins, scaffolding, temporary fencing, hoardings, dust barriers, port-a-loo on site, electrical and water connections during the build. On a major renovation these add up to between $5,000 and $15,000. They should be in the contract. Ask.

Demolition surprises

Older Canberra homes, particularly anything pre-1985, can hide asbestos in eaves, cornices, vinyl flooring, fibro sheeting and more. ACT asbestos removal requires a licensed contractor and can add $5,000 to $25,000 if it’s discovered during demolition. The Mr Fluffy era is its own beast - if you suspect Mr Fluffy contamination, that’s a separate conversation entirely. I’ve written about Mr Fluffy block rebuilds here.

Structural surprises

Once walls come down, what’s behind them sometimes isn’t what the plans assumed. Rotted bearers, undersized beams, slumped slabs, poor existing footings. A well-experienced builder will price a contingency for this on older homes, but the surprises still happen. Budget 10-15% contingency on top of your contract price for any structural renovation.

Council and certifier fees

DA fees, building certifier inspections, surveyor fees, energy efficiency reports, traffic management plans for some streetscapes. These are usually $3,000 to $10,000 across a full project. Sometimes they’re in the builder’s contract, sometimes they’re owner-supplied. Check.

Connections and services

Electrical upgrades from single to three-phase, water meter upgrades, NBN rerouting, stormwater detention. Most homeowners assume the existing services are fine. Often they aren’t. Allow $5,000 to $20,000 for service upgrades on bigger projects.

Worth flagging on gas specifically: the ACT is phasing gas out of the residential network, so new gas connections aren’t happening and gas appliance replacements are increasingly restricted. If your existing home has gas and you’re relocating services during a renovation, plan for the cost of either relocating the existing line or switching to all-electric. Going all-electric from the outset is usually the cleaner call, and the induction cooktop/heat-pump hot water/reverse-cycle stack is now genuinely excellent.

Moving out costs

If you can’t live in the home during the build, you need to budget for rental accommodation, removalists, double rates and bills. A six month rental in Canberra inner-north is $25,000 to $35,000. Storage of furniture is another $1,500 to $3,500. Often these are bigger than people expect.

Furniture, blinds, landscaping and finishing

The contract gets you to handover. It doesn’t get you to “the home is ready to live in.” Window furnishings, new furniture, landscaping, fencing, driveways, replanting and reinstating front gardens after construction traffic - all of these are extra. On a major renovation, plan another $30,000 to $80,000 for completing the home after handover.

For the full breakdown of what catches people out, my 12 hidden renovation costs in Canberra article goes deeper.

Light-filled hallway with new timber floorboards and a hydronic heating panel in a Campbell renovation
A renovated hallway in Campbell. Heating, wiring and plumbing upgrades are where hidden costs most often surface.
Next · Chapter 04Setting realistic timelines

Chapter 04

4. Setting realistic timelines

On-site duration versus total elapsed time for seven project types, and what compresses or extends them.

The other place expectations get crushed is timelines. Renovations take longer than people think, every single time. Here’s what I see in practice.

Realistic durations by project type
Project typeRealistic on-site durationTotal elapsed time including planning & approvals0102030 months
Bathroom renovation4-7 weeks3-5 months
Kitchen renovation6-10 weeks4-7 months
Whole-house cosmetic refresh10-16 weeks5-9 months
Major structural renovation6-10 months12-20 months
Single-storey extension5-8 months11-17 months
Second storey addition7-11 months14-24 months
Knockdown rebuild12-16 months20-30 months

Whole project, planning to handoverConstruction on site

Why “elapsed time” matters more than “build time”

Most homeowners hear “the build will take six months” and start planning their lives around that number. But before the build starts there’s a designer phase (1-3 months), a documentation phase (1-2 months), a DA approval window (8-16 weeks for anything that needs one), a tendering and contract phase (3-6 weeks), and a builder lead time (1-3 months for a quality builder with a backlog). All of that happens before the first sledgehammer swings.

If you’re starting conversations with a builder today, a major renovation realistically isn’t completed inside 14 months.

Plan accordingly. Builders who promise dramatically shorter timelines are usually about to disappoint you.

Things that compress timelines

  • Decisions made early and not changed
  • A clear, locked scope with no open variables
  • Selections (tiles, fixtures, paint colours, hardware) finalised before the build starts
  • Working with a builder who has reliable trade relationships
  • Living off-site so trades can work flat out

Things that extend timelines

  • Mid-build variations and changes of mind
  • Late selections (this is the single biggest cause of delays I see)
  • Custom-made items with long lead times (joinery, stone benchtops, imported tiles)
  • Living on-site through the build
  • DA conditions that require additional work
  • Weather delays in winter, particularly for slab and roof stages
Three Rentoule Projects team members checking a tablet in a framed and insulated room on site
Checking the programme on site. Construction is only the final stage of the timeline.
Next · Chapter 05Choosing the right builder

Chapter 05

5. Choosing the right builder

Five things to check before you sign with anyone, us included.

If you only get one decision right in the whole process, make it this one. The right builder turns a stressful project into a great one. The wrong builder turns a great project into a disaster.

Here’s what to look for. I’ve written a full 10-question guide on builder selection, but the short version is below.

Licence and insurance

In the ACT, residential builders need to be licensed by Access Canberra. The licence number should be on every quote and contract. Insurance should include public liability, contract works, and home warranty insurance for jobs over $12,000. If a builder can’t show you these documents, walk away.

Fixed price, not cost-plus

Cost-plus contracts (where you pay all costs plus the builder’s margin) sound flexible. They’re not. They transfer all the price risk to you. A reputable builder will quote a fixed price and stand behind it. Variations are negotiated transparently when scope changes, but the base contract is locked.

Every contract I sign at Rentoule Projects is fixed-price. It’s harder for me, because I have to estimate accurately and absorb my own mistakes. That’s the point. It means you know exactly where you stand. See how we get to a fixed price.

References from completed work

Anyone can show you finished photos. Ask for the contact details of two clients whose projects have been finished for at least 12 months. Ring them. Ask: did the project finish on time, did it finish on budget, did the builder fix things that came up after handover, and would you use them again? Three minutes on the phone tells you more than three days of marketing.

Site presence

Ask who will be on site daily. At Rentoule Projects, we have a site manager running each active build day to day. I’m across every project but I’m not standing on site - I’m running the business, talking with new clients, handling design and contract decisions. Some builders never come on site at all. Some operate as foremen running the actual labour. Both can work, but you need to know which model you’re hiring.

Communication standards

How will you hear about progress? How quickly do they respond to questions? How are decisions documented? A great builder has a system. A poor builder makes you chase them. If you’re already chasing them during the quoting stage, that’s the relationship you’ll have for nine months.

Two Rentoule Projects team members walking and talking on a verandah during a renovation
On site during a renovation. Ask any builder who will be on your site day to day.
Next · Chapter 06Designing for the next 20 years

Chapter 06

6. Designing for the next 20 years

Five traits shared by Canberra renovations that age well.

The renovations that age well in Canberra share a few traits. The ones that look dated in five years also share a few traits.

Orientation and natural light

This is the single biggest design lever in Canberra. North-facing living spaces, properly designed for our seasonal sun angles, are warm in winter without heating and cool in summer with the right eaves. Get this right and your home performs better, costs less to run, and feels better to live in. Get this wrong and you’re fighting your house with energy bills for the next two decades.

If your existing home faces the wrong way, a renovation is your chance to redesign around the sun. Sometimes that means moving the kitchen and living areas. It’s worth it.

Energy performance

New homes in the ACT must meet 7 stars under NatHERS, and extensions have to meet the energy requirements for the new work. Going beyond 7 stars can cost less than people expect when it is designed in from the start, and it pays back in lower heating bills. Insulate above the minimum, double-glaze (or triple-glaze for north-facing glass), seal the building envelope properly, install efficient reverse-cycle heating and cooling. My energy efficiency guide goes deeper on this.

Layout that flexes

The home you need at 35 with two kids isn’t the home you need at 50 with teenagers, or 65 with grown-up children visiting. Good design accommodates change. Spaces that can change function (a study that becomes a guest room, an open plan that can be partitioned, a downstairs bedroom that becomes a bedroom for ageing parents). Avoid hyper-specific spaces that lock the home into one phase of life.

Materials that age

The fashionable choice today is the dated choice in five years. The classics rarely date. Timber, stone, brick, plaster, neutral palettes, durable hardware. Save the trend-driven choices for elements you can change cheaply (cushions, art, paint colour). Build the bones from materials that look better with time.

Indoor-outdoor connection

Canberra has a beautiful climate for outdoor living three seasons a year. Bifold or stacker doors that open the living space to a covered alfresco, properly sized for a dining table, oriented to catch afternoon sun, with shelter from the wind. This single design move adds more lifestyle value per dollar than almost anything else we build.

Skylights and exposed timber beams bringing daylight into a Holder living area
Skylights added in a Holder renovation bring daylight deep into the living area.
Next · Chapter 07Planning approvals and ACT regulations

Chapter 07

7. Planning approvals and ACT regulations

The three planning pathways, what usually needs a DA, Building Approval and NCC 2025.

The ACT’s planning system is its own creature. Here’s the broad shape, but my DA approval article has the full detail.

Three categories of planning approval

No planning approval needed

Most cosmetic work, internal renovations not affecting structure, small repairs. No planning approval, though the building codes still apply. Check with a certifier whether building approval is needed.

Exempt from a DA: the Single Dwelling Housing Development Control

Many single-house extensions, alterations and additions, including some second storeys, can go ahead without a Development Application if they fully comply with the Single Dwelling Housing Development Control and you have given written information about the work to the adjoining residents. You still need building approval. Where it suits the brief, this is the pathway we aim for, because it is quicker and more certain than a DA. Minor departures from the controls may suit an exemption declaration.

Development Application (DA)

Projects that can’t meet the exempt controls, heritage-affected sites, and anything beyond a single dwelling. Assessed by the Territory Planning Authority, so allow more time and less certainty than the exempt pathway.

Things that usually need a DA

  • Knockdown rebuilds that can’t meet the exempt development controls
  • Second storey additions that go beyond the height, envelope or setback controls (minor departures may suit an exemption declaration instead)
  • Changes to the front facade in suburbs with heritage or character overlay (Reid, Forrest, parts of Yarralumla and Griffith)
  • Anything reducing on-site car parking below required levels
  • Departures from the setback, envelope or site coverage controls that are too large for an exemption declaration

Building Approval (BA) is separate

Worth knowing: whichever planning pathway you take, you still need a separate Building Approval (BA) before any construction starts. The BA is issued by a private building certifier and confirms that your plans comply with the National Construction Code, structural requirements, energy efficiency rules and all the technical building standards. Even a fully exempt development typically still needs a BA if there’s actual building work involved. The BA process usually runs 2-4 weeks for straightforward projects and sits alongside or after your planning pathway. As your builder, we manage the BA process and certifier relationship on your behalf.

NCC 2025

The National Construction Code 2025 is now in force in the ACT, and becomes mandatory for building approvals from 1 May 2027. Projects with a DA lodged before 1 November 2026 can stay on NCC 2022. It introduces stricter requirements on energy efficiency, accessibility (the Livable Housing standard), and condensation management. For new builds and major renovations, NCC 2025 will add somewhere between $14,000 and $55,000 to project cost depending on scope. I’ve written a detailed guide here.

A Rentoule Projects carpenter fitting timber lining boards between insulated wall frames
Insulation in place and timber linings going up. What goes inside the walls is shaped by the building rules as much as the design.
Next · Chapter 08Queanbeyan, the region and beyond

Chapter 08

8. Queanbeyan, the surrounding region and beyond

Building either side of the ACT/NSW border, and when we consider the south coast.

Canberra is our primary market but worth knowing: I hold a NSW builder’s licence in addition to my ACT licence, so we regularly build in Queanbeyan, Jerrabomberra, Googong, Bungendore and the surrounding region.

A lot of our Canberra-raised clients end up moving just across the border for more land, lower prices or a specific lifestyle preference, and then want a builder who can deliver the same Canberra-level quality. We’re happy to bridge that. Build standards, contracts, communication, fixed-price approach - all identical either side of the ACT/NSW line.

For the right client and the right project, we’ll also consider work further afield on the south coast. It has to be a project worth travelling for and we’re selective about taking it on, but if your vision is a considered south coast build and you want a Canberra-quality builder who’ll stand behind the work, have the conversation with us anyway. See where we build.

Next · Chapter 09The five mistakes I see most often

Chapter 09

9. The five mistakes I see most often

After 19 years in the trade, the same patterns hurt the most.

After 19 years in this trade I see the same patterns over and over. Here are the five that hurt the most.

Mistake 1: Choosing the cheapest quote

The cheapest builder is usually the most expensive when it’s done. Either they’ve under-priced (and either lose money trying to deliver, or chase you for variations), or they’re cutting corners you can’t see. A quote that’s 20% lower than three other quotes for the same scope is a warning sign, not a win.

Mistake 2: Starting before the design is finished

“We’ll figure that out as we go” costs far more than figuring it out before the build. Every undecided detail becomes a delay or a variation. Lock the scope and the selections that drive the price, then start the build.

Mistake 3: Ignoring orientation

A beautifully designed kitchen on the wrong side of the house is a kitchen you’ll heat in winter and shade in summer for the next 20 years. The orientation conversation should happen at concept stage, not after plans are drawn.

Mistake 4: Underestimating the project length

Couples sign up to a “six month renovation” and find themselves at month nine, still living in temporary accommodation, paying double rates, and snapping at each other. Plan for the realistic duration in section 4, not the optimistic one. Build a buffer into your living arrangements.

Mistake 5: Picking finishes too early

The tile you fall in love with at concept stage is often discontinued by build time. Agree the type and allowance before you sign, then confirm the exact product in the 4-8 weeks before the relevant trade is on site. Check stock and lead times before you commit. Have a backup option for anything imported or custom-made.

Close-up of a carpenter marking out timber with a pencil and steel square
Marking out on site. Details settled early cost far less than details decided mid-build.
Next · Chapter 10Where to go from here

Chapter 10

10. Where to go from here

What to do next, depending on how far you are from starting.

If you’ve read this far, you’re more prepared than 90% of homeowners I meet. The next steps depend on where you are in the journey.

If you’re 12+ months from starting

Start collecting what you love. A Pinterest board, a folder of magazine pages, photos from friends’ homes, notes about what works and doesn’t work in your current home. Walk around suburbs you like (Griffith, Yarralumla, Forrest, Reid, Ainslie, Campbell, Turner, Braddon) and notice what good renovations look like. Read the cost guides linked above so you have realistic expectations.

If you’re 6-12 months out

Start conversations. With designers, with builders, maybe with a finance broker if you’ll need to borrow. Get a feasibility on your specific project. We do early-stage feasibility for most clients and it’s usually the most valuable money they spend on the project.

If you’re 3-6 months out

Lock in your design team and your builder. Begin documentation and approval pathway. Start finalising your major selections (cabinetry style, tile direction, key fixtures). The decisions you make now compound over the next 12 months.

If you’re ready to start

Get in touch. Even if you’re not sure we’re the right builder for your project, I’m happy to have a no-pressure conversation about your plans. Sometimes the best thing I can do for someone is point them at a builder who’s a better fit. Sometimes the best thing is to say “let’s talk.” Start a conversation or read how we work.

Either way, coffee’s on me.

Griffith main bathroom with green tile, brass tapware and twin black-framed mirrors
A finished main bathroom in Griffith.