This is the guide I wish every Canberra homeowner had before they started a renovation. Real costs, real timelines, real decisions, written by a licensed ACT builder with 19 years in the building industry and 5 years running my own business.
I’m Jeff Rentoule. I run Rentoule Projects, a small residential building business based in Canberra. Over the past five years I’ve watched too many homeowners walk into renovations carrying assumptions that cost them money, time, or both. This guide is my attempt to fix that. No corporate fluff, no sales pitch in disguise. Just what I would tell a mate over coffee if they were thinking about renovating.
Use it however you want. Read it end to end, jump to the section you need, or come back when a specific question comes up.
Chapter 01
1. The real cost of renovating in Canberra
Typical Canberra ranges for seven common project types, and why building here costs more than the eastern seaboard average.
Let’s start with the question everyone wants answered first. What does a renovation cost in Canberra in 2026?
The honest answer is “it depends.” But that’s a cop-out, so here are the ranges I see across our projects, broken out by the most common project types. These are turn-key, fixed-price figures including labour, materials, project management, and trade coordination.
| Project type | Typical Canberra range | What you get |
|---|---|---|
| Bathroom renovation | $35,000 to $130,000+ | Ensuites from $35,000, main bathrooms from $45,000. Full strip-out and rebuild, custom to premium fixtures |
| Kitchen renovation | $35,000 to $160,000+ | Small area kitchens from $35,000, full kitchens from $50,000. Most family kitchens with a wall removed sit at $90,000 to $120,000. Complete redesign, custom cabinetry, stone benchtops, quality appliances |
| Whole-house cosmetic refresh | $80,000 to $250,000 | Paint, flooring, kitchen, bathrooms, light fittings. No structural work (not a Rentoule Projects service) |
| Major renovation (structural) | $300,000 to $1,000,000+ | Walls moved, layout changed, new kitchen and bathrooms, possibly second storey |
| Single-storey extension | $150,000 to $450,000 | 30-60 sqm addition, usually living space or master suite, premium finishes |
| Second storey addition | $300,000 to $700,000+ | Full upper floor, structural reinforcement, internal stairs, often 2-3 bedrooms |
| Knockdown rebuild | $850,000 to $2M+ | Demolition, new build to your specification, typically 200-350 sqm |
For deeper detail on each, I’ve written separate cost guides:
- Home renovation costs in Canberra (the cornerstone cost guide)
- Full house renovation in Canberra (scope, sequencing and stay-vs-move-out)
- Bathroom renovation costs
- Kitchen renovation costs
- Home extension costs
Weighing up a full rebuild? See our knockdown rebuild service.
Why Canberra costs more than the eastern seaboard average
A smaller trade pool
Three reasons. First, the trade pool is smaller. Sydney and Melbourne have an order of magnitude more builders, plumbers, electricians and tilers competing for work. We don’t. When demand peaks, prices peak harder here.
Stricter ACT regulations
Second, ACT regulations are stricter than most states. Energy efficiency requirements (EER), bushfire compliance in many suburbs, asbestos protocols on older homes, and the ACT’s particular planning rules all add cost. They also add quality, but they add cost.
A brutal climate
Third, our climate is brutal. Canberra winters demand higher-spec insulation, double or triple glazing, sealed building envelopes, and reverse-cycle systems sized for sub-zero overnights. A renovation that ignores climate performance is a renovation you’ll regret in July.

Chapter 02
2. How to plan your renovation properly
The five-step sequence that works, from writing the brief to locking the scope before you sign.
The biggest predictor of how a renovation goes is how much thought went in before a single trade arrived on site. Most disasters I’ve seen started with rushed planning.
Here’s the sequence that works.
Step 1: Define the brief in writing
Before you talk to anyone, write down what you want. Not “a bigger kitchen” - write down “I want an open-plan kitchen, dining and living area where the kids can do homework while I cook, with a butler’s pantry hidden from view, and a north-facing dining nook with morning sun.” The more specific you are, the easier every conversation downstream becomes.
If you can’t write your brief, you’re not ready to start. That’s not a failing - it just means the next step is conversations, not contracts.
Step 2: Set a budget you can defend
Most people set a budget by guessing what they can afford and then assuming a renovation will fit. That’s backwards. Start with the cost ranges in section 1, work out what your project realistically costs, then check whether your finance and savings cover it with a 15% buffer for variations and surprises.
If the numbers don’t work, you have three options: reduce scope, find more money, or wait. Pretending the numbers work is the most expensive option, because it leads to either a half-finished project or compromises that ruin the result.
Step 3: Get the right professionals involved early
For anything beyond a simple cosmetic refresh, you need three people in the room: a designer or architect, a builder, and a structural engineer if walls are coming out. Get all three involved before drawings are finalised. I’ve watched homeowners spend $15,000 on architectural plans only to discover the design isn’t buildable within their budget.
Some builders, including us, will do early-stage feasibility before you commit to detailed design. It saves money and frustration on both sides.
Step 4: Understand the approval pathway
Not every renovation needs a Development Application (DA), but you need to know which category yours falls into before you commit. Cosmetic and minor work often qualifies as exempt development. Structural work, extensions and second storeys may need DA approval, unless they fully comply with the exempt development rules. The rules in the ACT are specific. I’ve written a full guide on DA approvals here.
Step 5: Lock the scope before you sign
Every variation after a contract is signed costs more than it would have during planning. Sometimes a lot more. Spend the time up front to nail down inclusions, finishes, fixtures and fittings to the level of model numbers and brand names. The contract should have a defined scope, a fixed price, a payment schedule, a completion date with liquidated damages, and a written variations process.
If you want to go deeper, my step-by-step planning guide walks through the full process. And if you’d like to see how we run planning and pricing on our own projects, here’s how we work.

Chapter 04
4. Setting realistic timelines
On-site duration versus total elapsed time for seven project types, and what compresses or extends them.
The other place expectations get crushed is timelines. Renovations take longer than people think, every single time. Here’s what I see in practice.
| Project type | Realistic on-site duration | Total elapsed time including planning & approvals | 0102030 months |
|---|---|---|---|
| Bathroom renovation | 4-7 weeks | 3-5 months | |
| Kitchen renovation | 6-10 weeks | 4-7 months | |
| Whole-house cosmetic refresh | 10-16 weeks | 5-9 months | |
| Major structural renovation | 6-10 months | 12-20 months | |
| Single-storey extension | 5-8 months | 11-17 months | |
| Second storey addition | 7-11 months | 14-24 months | |
| Knockdown rebuild | 12-16 months | 20-30 months |
Whole project, planning to handoverConstruction on site
Why “elapsed time” matters more than “build time”
Most homeowners hear “the build will take six months” and start planning their lives around that number. But before the build starts there’s a designer phase (1-3 months), a documentation phase (1-2 months), a DA approval window (8-16 weeks for anything that needs one), a tendering and contract phase (3-6 weeks), and a builder lead time (1-3 months for a quality builder with a backlog). All of that happens before the first sledgehammer swings.
If you’re starting conversations with a builder today, a major renovation realistically isn’t completed inside 14 months.
Plan accordingly. Builders who promise dramatically shorter timelines are usually about to disappoint you.
Things that compress timelines
- Decisions made early and not changed
- A clear, locked scope with no open variables
- Selections (tiles, fixtures, paint colours, hardware) finalised before the build starts
- Working with a builder who has reliable trade relationships
- Living off-site so trades can work flat out
Things that extend timelines
- Mid-build variations and changes of mind
- Late selections (this is the single biggest cause of delays I see)
- Custom-made items with long lead times (joinery, stone benchtops, imported tiles)
- Living on-site through the build
- DA conditions that require additional work
- Weather delays in winter, particularly for slab and roof stages

Chapter 05
5. Choosing the right builder
Five things to check before you sign with anyone, us included.
If you only get one decision right in the whole process, make it this one. The right builder turns a stressful project into a great one. The wrong builder turns a great project into a disaster.
Here’s what to look for. I’ve written a full 10-question guide on builder selection, but the short version is below.
Licence and insurance
In the ACT, residential builders need to be licensed by Access Canberra. The licence number should be on every quote and contract. Insurance should include public liability, contract works, and home warranty insurance for jobs over $12,000. If a builder can’t show you these documents, walk away.
Fixed price, not cost-plus
Cost-plus contracts (where you pay all costs plus the builder’s margin) sound flexible. They’re not. They transfer all the price risk to you. A reputable builder will quote a fixed price and stand behind it. Variations are negotiated transparently when scope changes, but the base contract is locked.
Every contract I sign at Rentoule Projects is fixed-price. It’s harder for me, because I have to estimate accurately and absorb my own mistakes. That’s the point. It means you know exactly where you stand. See how we get to a fixed price.
References from completed work
Anyone can show you finished photos. Ask for the contact details of two clients whose projects have been finished for at least 12 months. Ring them. Ask: did the project finish on time, did it finish on budget, did the builder fix things that came up after handover, and would you use them again? Three minutes on the phone tells you more than three days of marketing.
Site presence
Ask who will be on site daily. At Rentoule Projects, we have a site manager running each active build day to day. I’m across every project but I’m not standing on site - I’m running the business, talking with new clients, handling design and contract decisions. Some builders never come on site at all. Some operate as foremen running the actual labour. Both can work, but you need to know which model you’re hiring.
Communication standards
How will you hear about progress? How quickly do they respond to questions? How are decisions documented? A great builder has a system. A poor builder makes you chase them. If you’re already chasing them during the quoting stage, that’s the relationship you’ll have for nine months.

Chapter 06
6. Designing for the next 20 years
Five traits shared by Canberra renovations that age well.
The renovations that age well in Canberra share a few traits. The ones that look dated in five years also share a few traits.
Orientation and natural light
This is the single biggest design lever in Canberra. North-facing living spaces, properly designed for our seasonal sun angles, are warm in winter without heating and cool in summer with the right eaves. Get this right and your home performs better, costs less to run, and feels better to live in. Get this wrong and you’re fighting your house with energy bills for the next two decades.
If your existing home faces the wrong way, a renovation is your chance to redesign around the sun. Sometimes that means moving the kitchen and living areas. It’s worth it.
Energy performance
New homes in the ACT must meet 7 stars under NatHERS, and extensions have to meet the energy requirements for the new work. Going beyond 7 stars can cost less than people expect when it is designed in from the start, and it pays back in lower heating bills. Insulate above the minimum, double-glaze (or triple-glaze for north-facing glass), seal the building envelope properly, install efficient reverse-cycle heating and cooling. My energy efficiency guide goes deeper on this.
Layout that flexes
The home you need at 35 with two kids isn’t the home you need at 50 with teenagers, or 65 with grown-up children visiting. Good design accommodates change. Spaces that can change function (a study that becomes a guest room, an open plan that can be partitioned, a downstairs bedroom that becomes a bedroom for ageing parents). Avoid hyper-specific spaces that lock the home into one phase of life.
Materials that age
The fashionable choice today is the dated choice in five years. The classics rarely date. Timber, stone, brick, plaster, neutral palettes, durable hardware. Save the trend-driven choices for elements you can change cheaply (cushions, art, paint colour). Build the bones from materials that look better with time.
Indoor-outdoor connection
Canberra has a beautiful climate for outdoor living three seasons a year. Bifold or stacker doors that open the living space to a covered alfresco, properly sized for a dining table, oriented to catch afternoon sun, with shelter from the wind. This single design move adds more lifestyle value per dollar than almost anything else we build.

Chapter 07
7. Planning approvals and ACT regulations
The three planning pathways, what usually needs a DA, Building Approval and NCC 2025.
The ACT’s planning system is its own creature. Here’s the broad shape, but my DA approval article has the full detail.
Three categories of planning approval
No planning approval needed
Most cosmetic work, internal renovations not affecting structure, small repairs. No planning approval, though the building codes still apply. Check with a certifier whether building approval is needed.
Exempt from a DA: the Single Dwelling Housing Development Control
Many single-house extensions, alterations and additions, including some second storeys, can go ahead without a Development Application if they fully comply with the Single Dwelling Housing Development Control and you have given written information about the work to the adjoining residents. You still need building approval. Where it suits the brief, this is the pathway we aim for, because it is quicker and more certain than a DA. Minor departures from the controls may suit an exemption declaration.
Development Application (DA)
Projects that can’t meet the exempt controls, heritage-affected sites, and anything beyond a single dwelling. Assessed by the Territory Planning Authority, so allow more time and less certainty than the exempt pathway.
Things that usually need a DA
- Knockdown rebuilds that can’t meet the exempt development controls
- Second storey additions that go beyond the height, envelope or setback controls (minor departures may suit an exemption declaration instead)
- Changes to the front facade in suburbs with heritage or character overlay (Reid, Forrest, parts of Yarralumla and Griffith)
- Anything reducing on-site car parking below required levels
- Departures from the setback, envelope or site coverage controls that are too large for an exemption declaration
Building Approval (BA) is separate
Worth knowing: whichever planning pathway you take, you still need a separate Building Approval (BA) before any construction starts. The BA is issued by a private building certifier and confirms that your plans comply with the National Construction Code, structural requirements, energy efficiency rules and all the technical building standards. Even a fully exempt development typically still needs a BA if there’s actual building work involved. The BA process usually runs 2-4 weeks for straightforward projects and sits alongside or after your planning pathway. As your builder, we manage the BA process and certifier relationship on your behalf.
NCC 2025
The National Construction Code 2025 is now in force in the ACT, and becomes mandatory for building approvals from 1 May 2027. Projects with a DA lodged before 1 November 2026 can stay on NCC 2022. It introduces stricter requirements on energy efficiency, accessibility (the Livable Housing standard), and condensation management. For new builds and major renovations, NCC 2025 will add somewhere between $14,000 and $55,000 to project cost depending on scope. I’ve written a detailed guide here.

Chapter 08
8. Queanbeyan, the surrounding region and beyond
Building either side of the ACT/NSW border, and when we consider the south coast.
Canberra is our primary market but worth knowing: I hold a NSW builder’s licence in addition to my ACT licence, so we regularly build in Queanbeyan, Jerrabomberra, Googong, Bungendore and the surrounding region.
A lot of our Canberra-raised clients end up moving just across the border for more land, lower prices or a specific lifestyle preference, and then want a builder who can deliver the same Canberra-level quality. We’re happy to bridge that. Build standards, contracts, communication, fixed-price approach - all identical either side of the ACT/NSW line.
For the right client and the right project, we’ll also consider work further afield on the south coast. It has to be a project worth travelling for and we’re selective about taking it on, but if your vision is a considered south coast build and you want a Canberra-quality builder who’ll stand behind the work, have the conversation with us anyway. See where we build.
Chapter 09
9. The five mistakes I see most often
After 19 years in the trade, the same patterns hurt the most.
After 19 years in this trade I see the same patterns over and over. Here are the five that hurt the most.
Mistake 1: Choosing the cheapest quote
The cheapest builder is usually the most expensive when it’s done. Either they’ve under-priced (and either lose money trying to deliver, or chase you for variations), or they’re cutting corners you can’t see. A quote that’s 20% lower than three other quotes for the same scope is a warning sign, not a win.
Mistake 2: Starting before the design is finished
“We’ll figure that out as we go” costs far more than figuring it out before the build. Every undecided detail becomes a delay or a variation. Lock the scope and the selections that drive the price, then start the build.
Mistake 3: Ignoring orientation
A beautifully designed kitchen on the wrong side of the house is a kitchen you’ll heat in winter and shade in summer for the next 20 years. The orientation conversation should happen at concept stage, not after plans are drawn.
Mistake 4: Underestimating the project length
Couples sign up to a “six month renovation” and find themselves at month nine, still living in temporary accommodation, paying double rates, and snapping at each other. Plan for the realistic duration in section 4, not the optimistic one. Build a buffer into your living arrangements.
Mistake 5: Picking finishes too early
The tile you fall in love with at concept stage is often discontinued by build time. Agree the type and allowance before you sign, then confirm the exact product in the 4-8 weeks before the relevant trade is on site. Check stock and lead times before you commit. Have a backup option for anything imported or custom-made.

Chapter 10
10. Where to go from here
What to do next, depending on how far you are from starting.
If you’ve read this far, you’re more prepared than 90% of homeowners I meet. The next steps depend on where you are in the journey.
If you’re 12+ months from starting
Start collecting what you love. A Pinterest board, a folder of magazine pages, photos from friends’ homes, notes about what works and doesn’t work in your current home. Walk around suburbs you like (Griffith, Yarralumla, Forrest, Reid, Ainslie, Campbell, Turner, Braddon) and notice what good renovations look like. Read the cost guides linked above so you have realistic expectations.
If you’re 6-12 months out
Start conversations. With designers, with builders, maybe with a finance broker if you’ll need to borrow. Get a feasibility on your specific project. We do early-stage feasibility for most clients and it’s usually the most valuable money they spend on the project.
If you’re 3-6 months out
Lock in your design team and your builder. Begin documentation and approval pathway. Start finalising your major selections (cabinetry style, tile direction, key fixtures). The decisions you make now compound over the next 12 months.
If you’re ready to start
Get in touch. Even if you’re not sure we’re the right builder for your project, I’m happy to have a no-pressure conversation about your plans. Sometimes the best thing I can do for someone is point them at a builder who’s a better fit. Sometimes the best thing is to say “let’s talk.” Start a conversation or read how we work.